Power Outage in Northriding, Johannesburg
Power Outages Affecting Northriding1 active
Updated 2m ago- Reported - Fri, 21 Aug, 08:12The Precision No2 Distributor at Northriding 11kv Substation tripped, causing an unplanned power interruption to customers in Kya Sand.source
- Update - Fri, 21 Aug, 11:2922% of the power supply has been restored due to a cable fault affecting customers in Kya Sand, and the test branch team is on site locating the fault.source
- Update - Fri, 21 Aug, 18:30Repairs are ongoing following a cable fault at Northriding 11kv Substation's Precision No.2 Distributor, affecting customers in Kya Sands, with power restorations remaining at 22%.source
- Reported - Mon, 17 Aug, 13:22An unplanned power outage originating from Northriding Substation on the Precision Distributor is affecting customers in Northriding and Kya Sand.source
- Reported - Tue, 18 Aug, 07:57An unplanned power supply interruption is affecting customers in Northriding AH and Kya Sand; operators have been informed to investigate the cause.source
- Update - Tue, 18 Aug, 17:40At Northriding Substation, the vandalised indoor transformer is installed, but a new mini substation must also be installed before restoration to customers in Aries Avenue, Scorpio Avenue, and Pluto CL.source
- Update - Tue, 18 Aug, 17:48Due to technical challenges, fault location has been halted, and the test branch is scheduled to continue tomorrow morning, affecting customers in Northriding AH and Kya Sand.source
- Update - Tue, 18 Aug, 18:32Team is currently busy on site with mini substation installation, cable wiring, and tests will then follow before restoration can commence.source
- Update - Wed, 19 Aug, 19:59The contractor is busy with the last jointing for the Precision Distributor at Northriding Substation, affecting Northriding AH and Kya Sand, due to stolen cables. Restoration remains at 22%.source
- Update - Thu, 20 Aug, 09:04Repairs are in progress following an outage caused by a cable fault affecting customers in Northriding AH and Kya Sand.source
- Reported - Thu, 20 Aug, 18:16A suspected power outage is affecting customers in Kya Sands, with operators being dispatched to investigate and restore supply.source
- Update - Thu, 20 Aug, 19:39Due to safety concerns, the outage affecting customers in Kya Sands will be attended to tomorrow morning by the day shift team.source
- Restored - Fri, 21 Aug, 21:58Power is fully restored to customers in Kya Sands following an outage caused by a cable fault.source
- Reported - Thu, 20 Aug, 22:10Operators are investigating the cause of an outage affecting customers in Northriding, Northwold, and Northgate from Olivedale Clinic Switching Station.source
- Restored - Thu, 20 Aug, 23:54Power has been fully restored to customers in Northriding, Northwold, Northgate.source
- Update - Wed, 19 Aug, 10:26The replacement of a vandalized minisubstation at Northriding Substation affecting customers in Sundowner is still in progress.source
- Restored - Wed, 19 Aug, 16:42Power supply has been fully restored at Northriding Substation to customers in Olievenhout, after an outage caused by a vandalised transformer.source
- Reported - Sat, 15 Aug, 10:37An outage at Northriding Substation's Preccission No.2 Distributor is affecting customers in Northriding AH and Kya Sand, with operators dispatched to investigate the cause.source
- Update - Sun, 16 Aug, 11:34Tests are being conducted on the Preccission No.2 Distributor at Northriding Substation before repairs can commence, affecting customers in Northriding AH and Kya Sand.source
- Update - Mon, 17 Aug, 08:41A cable fault affecting customers in Northriding AH and Kya Sand has been located, and repairs will commence once material is delivered.source
- Update - Mon, 17 Aug, 11:52Repairs are underway at Northriding Substation's Preccission No.2 Distributor following an outage caused by a cable fault affecting customers in Northriding AH and Kya Sand.source
- Update - Mon, 17 Aug, 16:51Repairs have been completed on the cable fault at Northriding Substation's Preccission No.2 Distributor, which affected customers in Northriding AH and Kya Sand, and the cable is ready for restoration.source
- Restored - Mon, 17 Aug, 19:18Power has been fully restored to customers in Northriding AH and Kya Sand, following an outage caused by a cable fault.source
- Update - Mon, 17 Aug, 17:01Repairs have been completed at Houtkoppen Substation for an outage caused by a vandalised transformer on Platina Street in Jukskei Park, with final tests and restoration to commence.source
- Reported - Mon, 17 Aug, 20:57A power outage is affecting customers in Jukskei Park, Johannesburg North, and Northriding.source
- Reported - Tue, 18 Aug, 09:12An outage at Houtkoppen Substation affecting customers in Jukskei Park and Johannesburg North. The test branch team has been requested to conduct tests on MSS 189 Platina Street.source
- Update - Tue, 18 Aug, 12:39At Houtkoppen Substation, a faulty switch was detected, affecting customers in Jukskei Park and Johannesburg North. A new switch is being sourced for replacement.source
- Update - Tue, 18 Aug, 17:43The transformer tested positive at Houtkoppen Substation, but a faulty Ring Main Unit (RMU) switch needs replacement; supply is temporarily restored via a generator for customers in Jukskei Park and Johannesburg North.source
- Reported - Tue, 18 Aug, 11:32An unplanned power supply interruption is affecting customers in Northriding AH and Kya Sand, with operators on site investigating the cause.source
- Reported - Tue, 18 Aug, 12:51The Precision Distributor at Northriding 11kv Substation tripped due to a cable fault, causing an unplanned power supply interruption in Northriding AH and Kya Sand.source
Other outages in this area
Reports from nearby suburbs in the same City Power service area. Not necessarily affecting Northriding directly.
Johannesburg Power Outages Today5 active
Updated 2m ago- Reported - Fri, 21 Aug, 18:13Brynorth Substation tripped on the Eskom side, causing a power interruption for customers in Bryanston.source
- Update - Sat, 22 Aug, 03:41Eskom has completed testing, and City Power teams will now conduct tests before restoration can commence, continuing to affect customers in Bryanston.source
- Reported - Sat, 22 Aug, 09:10An outage at Brynorth Substation's Incomer Number 2 is affecting customers in Bryanston, with repairs pending completion at Deinfern Substation.source
- Reported - Fri, 21 Aug, 05:35An unplanned power interruption is affecting customers in Dainfern, and operators have been informed to investigate the cause.source
- Update - Fri, 21 Aug, 09:29The appointed contractor is on site conducting repairs on a cable fault affecting customers in Dainfern Ridge.source
- Update - Fri, 21 Aug, 11:38The appointed contractor is on site conducting repairs on a cable fault affecting customers in Dainfern Ridge.source
Report a Power Outage in Northriding
Is your power off in Northriding? Report it to City Power so they can dispatch a team.
When Will Electricity Come Back in Northriding?
How long a power outage in Northriding takes to fix depends on what caused it. These are the typical restoration times for the three fault categories City Power handles.
- Unplanned fault
- Most outages in Northriding fixed within 4-8 hours. Minor faults (tripped circuit) take 2-4 hours.
- Cable theft
- 12-48 hours to repair, especially if specialised equipment is needed.
- Planned work
- City Power notifies Northriding residents in advance. Usually 6-10 hours during the day.
Power Outage History for Northriding (Last 90 Days)
City Power reported 10 outages affecting Northriding in the last 90 days. Most faults traced back to the Northriding Substation substation (3 of 10). The most common cause was cable fault.
| Date | Duration | Substation | Cause | Also affected |
|---|---|---|---|---|
| 14 Aug 2026 | - | Houtkoppen Substation | faulty overhead lines | Kya Sand |
| 13 Aug 2026 | - | Bernie Switching Station | overhead line fault | Kya Sand |
| 12 Aug 2026 | - | Bernie Switching Station | overload | Kya Sand |
| 11 Aug 2026 | - | Northriding 11kv Substation | overcurrent trip | Kya Sand |
| 08 Aug 2026 | 1.4d | Northriding Substation | cable fault | - |
| 08 Aug 2026 | - | Northriding Substation | planned maintenance | Deco Park, Noordhang, Business Park, New Market Road |
| 06 Aug 2026 | - | New Market Switching Station | planned maintenance | - |
| 05 Aug 2026 | - | Northriding Substation | faulty cable | NORTHGATE |
| 05 Aug 2026 | - | Northriding 11kv Substation | - | NORTHGATE |
| 02 Aug 2026 | 3.5h | - | cable fault | Northwold, Sundowner |
What to Do During a Power Outage in Northriding
Quick checklist to follow while waiting for City Power to restore power in Northriding.
- Switch off appliances at the wall to prevent damage from power surges when electricity returns.
- Leave one light switched on so you know when power is restored.
- Keep fridges and freezers closed - food stays cold for 4-6 hours if unopened.
- Use battery-powered lights instead of candles to reduce fire risk.
- Report the outage to City Power on 0114907484 / 0860562874 if it has not been reported yet.
Frequently Asked Questions About Power Outages in Northriding
Is there a power outage in Northriding right now?
Yes, there is currently a power outage reported in Northriding, Johannesburg. City Power is aware and working on restoration. Check the live updates above for the latest status and estimated restoration time.
How do I report a power outage in Northriding?
Call City Power on 0114907484 / 0860562874 to report a power outage in Northriding. You can also report online at citypower.co.za or follow @CityPowerJhb on X (Twitter) for updates.
How long do power outages last in Northriding?
Most unplanned power outages in Northriding are fixed within 4-8 hours. Minor faults like tripped circuits are often restored in 2-4 hours. Major faults from cable theft or equipment damage can take 12-48 hours. Planned maintenance typically lasts 6-10 hours during the day.
When will the electricity be back on in Northriding?
For the active outage affecting electricity in Northriding, see the live update at the top of this page for City Power's latest restoration estimate. Most unplanned electricity outages in Northriding restore within 4-8 hours. Call 0114907484 / 0860562874 to confirm the ETA for your specific street.
Is it load shedding or a power outage in Northriding?
If your power is off outside the load shedding schedule, Northriding is experiencing an unplanned power outage - not load shedding. Load shedding follows a fixed timetable, while power outages are caused by faults, cable theft, or equipment failure. Check Northriding load shedding schedule
What number do I call for City Power in Northriding?
Call City Power on 0114907484 / 0860562874 for power outages in Northriding. You can also report faults online at citypower.co.za or WhatsApp the relevant SDC channel for your area.
Related Pages
Click here to join our telegram channel and stay up to date with load shedding and related news!