Power Outage in Northriding, Johannesburg
Power Outages Affecting Northriding1 active
Updated 3m ago- Reported - Sat, 06 Jun, 13:19An unplanned power outage from Randburg Substation's Hawken Distributor is affecting customers in Bromhof, Boskuin, Northwold, Strijdompark, and Randparkrif.source
- Update - Sat, 06 Jun, 14:54Operators are on site investigating the cause of the power outage affecting customers at Bromhof, Boskuin, Northwold, Strijdompark, and Randparkrif.source
- Update - Sat, 06 Jun, 15:36The power supply has been partially restored to customers at Bromhof, Boskuin, Northwold, Strijdompark, and Randparkrif via the Hawken Distributor, with three load centres remaining off until the fault is located and repaired.source
- Update - Sat, 06 Jun, 17:55Operators will attend to the fault at Randburg Substation's Hawken Distributor once work at Northriding Substation is complete, affecting customers in Bromhof, Boskruin, Northwold, Strijdom Park, and Randpark Ridge.source
- Update - Sat, 06 Jun, 19:46Operators are on site attending to the remaining three load centres that are still off, affecting customers in Bromhof, Boskruin, Northwold, Strijdom Park, and Randpark Ridge.source
- Update - Sun, 07 Jun, 01:1074% of the power supply has been restored to customers in Bromhof, Boskruin, Northwold, Strijdom Park, and Randpark Ridge via the Hawken Distributor at Randburg Substation.source
- Update - Sun, 07 Jun, 09:57Supply has been restored to 74% of Bromhof, Randpark Ridge, Boskruin, Sonneglans, and Northwold. Multiple faults are being addressed at the substation, and a burnt cable is causing outages in Golden Harvest.source
- Reported - Fri, 05 Jun, 13:34Northriding 11 kv Substation's Precision Distributor tripped on earth fault, causing an unplanned power interruption affecting customers in Northriding AH and Kya Sands.source
- Reported - Fri, 05 Jun, 17:02An outage at Northriding 11 kv Substation's Precision Distributor is affecting customers in Northriding AH and Kya Sands. A test branch team will be requested tomorrow morning to locate the fault before repairs commence.source
- Update - Sat, 06 Jun, 08:47The test branch team has been requested to locate the fault at Northriding 11 kv Substation's Precision Distributor, affecting customers in Northriding AH and Kya Sands.source
- Update - Sat, 06 Jun, 09:37The test branch is on site locating a fault at Northriding 11 kv Substation's Precision Distributor, affecting customers in Northriding AH and Kya Sands.source
- Restored - Sat, 06 Jun, 11:08The fault has been located and repairs are in progress at Northriding 11 kv Substation's Precision Distributor, affecting customers in Northriding AH and Kya Sands. Power supply is anticipated to be restored by 21:00 tonight.source
- Update - Sat, 06 Jun, 15:52Repairs have been completed at Northriding 11 kv Substation's Precision Distributor, affecting customers in Northriding AH and Kya Sands; operators will conduct final tests before restoration.source
- Restored - Sat, 06 Jun, 19:28Power has been fully restored to customers in Northriding AH and Kya Sands via the Precision Distributor after a cable fault.source
- Update - Mon, 01 Jun, 21:01Power has been restored up to 80% at New Market 189 Switching Station, affecting customers on Epsom Road and Felstead Street; the remaining percentage will be attended to in the morning due to lack of access.source
- Restored - Tue, 02 Jun, 19:44Power has been fully restored in Hoogland and Northriding AH, following an outage at New Market 189 Switching Station caused by a cable fault.source
- Reported - Wed, 03 Jun, 19:40An outage at Houtkoppen Substation's Conduit Distributor is affecting customers at Jukskei Park, Northriding, and JHB North. Operators have been notified and will investigate.source
- Reported - Thu, 04 Jun, 05:22An unplanned power interruption is affecting Jukskei Park, Johannesburg North, and Bloubosrand, and operators have been informed to investigate.source
- Update - Thu, 04 Jun, 08:32A fault has been located by the test branch team, affecting Jukskei Park, Johannesburg North, Bloubosrand, and Maroeladal via the Conduit Distributor at Houtkoppen Substation, and a contractor is sourcing material for repairs.source
- Update - Thu, 04 Jun, 10:47A contractor is on site at Houtkoppen Substation's Conduit Distributor exposing the cable to conduct repairs on a cable fault, affecting Jukskei Park, Johannesburg North, Bloubosrand, and Maroeladal.source
- Update - Thu, 04 Jun, 13:11Repairs are underway at Houtkoppen Substation's Conduit Distributor following an outage caused by a cable fault, affecting Jukskei Park, Johannesburg North, Bloubosrand, and Maroeladal.source
- Update - Tue, 02 Jun, 08:34Operators have restored 88% of the power supply due to a cable fault affecting customers in Northriding AH and Hoogland.source
- Update - Tue, 02 Jun, 10:06A cable fault has been located on the New Market Distributor at Northriding Substation, affecting customers in Northriding, and repairs are underway.source
- Update - Tue, 02 Jun, 12:34Repairs are in progress at Northriding Substation's New Market Distributor following an outage affecting customers in Northriding.source
Other outages in this area
Reports from nearby suburbs in the same City Power service area. Not necessarily affecting Northriding directly.
Johannesburg Power Outages Today1 planned
Updated 3m ago
Report a Power Outage in Northriding
Is your power off in Northriding? Report it to City Power so they can dispatch a team.
When Will Electricity Come Back in Northriding?
How long a power outage in Northriding takes to fix depends on what caused it. These are the typical restoration times for the three fault categories City Power handles.
- Unplanned fault
- Most outages in Northriding fixed within 4-8 hours. Minor faults (tripped circuit) take 2-4 hours.
- Cable theft
- 12-48 hours to repair, especially if specialised equipment is needed.
- Planned work
- City Power notifies Northriding residents in advance. Usually 6-10 hours during the day.
Power Outage History for Northriding (Last 90 Days)
City Power reported 10 outages affecting Northriding in the last 90 days, totalling 28.8 hours without power. Average restoration time was 7.2 hours. Most faults traced back to the Olivedale Substation substation (3 of 10). The most common cause was planned maintenance.
| Date | Duration | Substation | Cause | Also affected |
|---|---|---|---|---|
| 03 Jun 2026 | - | Olivedale Substation | planned maintenance | Olivedale, Sonneglans, Bryanston Ext 3, Johannesburg North +3 more |
| 01 Jun 2026 | - | Olivedale Substation | planned maintenance | Olivedale, Sonneglans, Bryanston Ext 3, Johannesburg North +3 more |
| 25 May 2026 | - | Northriding Substation | cable fault | Kya Sand |
| 25 May 2026 | - | Northriding 11kv Substation | overcurrent trip | Kya Sand |
| 25 May 2026 | 10.7h | Houtkoppen Substation | cable fault | - |
| 24 May 2026 | 1.4h | Houtkoppen Substation | cable fault | Kya Sand |
| 23 May 2026 | 13.7h | Houtkoppen substation | blown termination | Johannesburg North |
| 23 May 2026 | - | Houtkoppen Substation | - | Johannesburg North |
| 19 May 2026 | - | Olivedale Substation | planned maintenance | Olivedale, Sonneglans, Bryanston Ext 3, Johannesburg North +3 more |
| 14 May 2026 | 3h | Northriding Substation | faulty jumper | - |
What to Do During a Power Outage in Northriding
Quick checklist to follow while waiting for City Power to restore power in Northriding.
- Switch off appliances at the wall to prevent damage from power surges when electricity returns.
- Leave one light switched on so you know when power is restored.
- Keep fridges and freezers closed - food stays cold for 4-6 hours if unopened.
- Use battery-powered lights instead of candles to reduce fire risk.
- Report the outage to City Power on 0114907484 / 0860562874 if it has not been reported yet.
Frequently Asked Questions About Power Outages in Northriding
Is there a power outage in Northriding right now?
Yes, there is currently a power outage reported in Northriding, Johannesburg. City Power is aware and working on restoration. Check the live updates above for the latest status and estimated restoration time.
How do I report a power outage in Northriding?
Call City Power on 0114907484 / 0860562874 to report a power outage in Northriding. You can also report online at citypower.co.za or follow @CityPowerJhb on X (Twitter) for updates.
How long do power outages last in Northriding?
Most unplanned power outages in Northriding are fixed within 4-8 hours. Minor faults like tripped circuits are often restored in 2-4 hours. Major faults from cable theft or equipment damage can take 12-48 hours. Planned maintenance typically lasts 6-10 hours during the day.
When will the electricity be back on in Northriding?
For the active outage affecting electricity in Northriding, see the live update at the top of this page for City Power's latest restoration estimate. Most unplanned electricity outages in Northriding restore within 4-8 hours. Call 0114907484 / 0860562874 to confirm the ETA for your specific street.
Is it load shedding or a power outage in Northriding?
If your power is off outside the load shedding schedule, Northriding is experiencing an unplanned power outage - not load shedding. Load shedding follows a fixed timetable, while power outages are caused by faults, cable theft, or equipment failure. Check Northriding load shedding schedule
What number do I call for City Power in Northriding?
Call City Power on 0114907484 / 0860562874 for power outages in Northriding. You can also report faults online at citypower.co.za or WhatsApp the relevant SDC channel for your area.