Power Outage in Emmerentia North, Johannesburg
Other outages in this area
Reports from nearby suburbs in the same City Power service area. Not necessarily affecting Emmerentia North directly.
Johannesburg Power Outages Today4 active
Updated 2m ago- Reported - Fri, 14 Aug, 08:26An outage is affecting customers in Greenside and Parkview; operators will investigate at the substation after completing current duties at Mayfair Substation.source
- Update - Fri, 14 Aug, 16:29A test branch team has been dispatched to locate the fault on an outage that left customers in Greenside and Parkview without power supply.source
- Reported - Fri, 14 Aug, 17:31An outage at Parkhurst Substation affecting the Greenside South Distributor is impacting customers in Greenside, Parkview, and surrounding areas. A joint team is currently on site locating the fault.source
- Update - Fri, 14 Aug, 19:31A test branch team remains on site at Parkhurst Substation's Greenside South Distributor and repairs are in progress, affecting customers at Greenside and Parkview.source
- Update - Fri, 14 Aug, 21:22Repairs for the Greenside South Distributor at Parkhurst Substation will be carried out tomorrow morning, affecting customers in Greenside and Parkview.source
- Update - Wed, 12 Aug, 12:18Operators are investigating an outage at Hursthills Substation's Crosby distributor that occurred yesterday and affected Crosby, with adverse weather potentially causing delays.source
- Update - Thu, 13 Aug, 07:55Power has been partially restored in Crosby via the Crosby Distributor from Hursthll Substation following an indoor transformer fault, which now requires replacement.source
- Update - Thu, 13 Aug, 11:41Power supply has been partially restored to customers in Crosby following an outage caused by a faulty indoor transformer, with a team organizing a replacement unit and another connecting a generator for temporary power restoration.source
Report a Power Outage in Emmerentia North
Is your power off in Emmerentia North? Report it to City Power so they can dispatch a team.
When Will Electricity Come Back in Emmerentia North?
How long a power outage in Emmerentia North takes to fix depends on what caused it. These are the typical restoration times for the three fault categories City Power handles.
- Unplanned fault
- Most outages in Emmerentia North fixed within 4-8 hours. Minor faults (tripped circuit) take 2-4 hours.
- Cable theft
- 12-48 hours to repair, especially if specialised equipment is needed.
- Planned work
- City Power notifies Emmerentia North residents in advance. Usually 6-10 hours during the day.
Power Outage History for Emmerentia North (Last 90 Days)
City Power reported 3 outages affecting Emmerentia North in the last 90 days. Most faults traced back to the Roosevelt Substation substation (2 of 3). The most common cause was cable fault.
| Date | Duration | Substation | Cause | Also affected |
|---|---|---|---|---|
| 24 Jul 2026 | 16.9h | Roosevelt Substation | cable fault | Berario, Blackheath, Emmarentia, Emmerentia South +3 more |
| 07 Jul 2026 | 1d | Roosevelt Substation | equipment fault | Berario, Blackheath, Emmarentia, Emmerentia South |
| 24 May 2026 | - | Delta Substation | emergency maintenance | Berario, Newlands, Fairlands North, Newlands Standby +11 more |
What to Do During a Power Outage in Emmerentia North
Quick checklist to follow while waiting for City Power to restore power in Emmerentia North.
- Switch off appliances at the wall to prevent damage from power surges when electricity returns.
- Leave one light switched on so you know when power is restored.
- Keep fridges and freezers closed - food stays cold for 4-6 hours if unopened.
- Use battery-powered lights instead of candles to reduce fire risk.
- Report the outage to City Power on 0114907484 / 0860562874 if it has not been reported yet.
Frequently Asked Questions About Power Outages in Emmerentia North
Is there a power outage in Emmerentia North right now?
No power outage is currently reported by City Power for Emmerentia North, Johannesburg. This page updates every 10 minutes with live data from City Power. If your power is off, report it by calling 0114907484 / 0860562874.
How do I report a power outage in Emmerentia North?
Call City Power on 0114907484 / 0860562874 to report a power outage in Emmerentia North. You can also report online at citypower.co.za or follow @CityPowerJhb on X (Twitter) for updates.
How long do power outages last in Emmerentia North?
Most unplanned power outages in Emmerentia North are fixed within 4-8 hours. Minor faults like tripped circuits are often restored in 2-4 hours. Major faults from cable theft or equipment damage can take 12-48 hours. Planned maintenance typically lasts 6-10 hours during the day.
When will the electricity be back on in Emmerentia North?
City Power has not logged an active electricity outage in Emmerentia North right now. If your power is off, the issue may be local to your street or property. Call 0114907484 / 0860562874 or check this page again - it updates every 10 minutes with live electricity restoration data from City Power.
Is it load shedding or a power outage in Emmerentia North?
If your power is off outside the load shedding schedule, Emmerentia North is experiencing an unplanned power outage - not load shedding. Load shedding follows a fixed timetable, while power outages are caused by faults, cable theft, or equipment failure. Check Emmerentia North load shedding schedule
What number do I call for City Power in Emmerentia North?
Call City Power on 0114907484 / 0860562874 for power outages in Emmerentia North. You can also report faults online at citypower.co.za or WhatsApp the relevant SDC channel for your area.